Malaysia-Thailand Joint Development Area |
||||||||||||||||||||||||||||||||
Background
Widely known by the abbreviation JDA, the wedge-shaped Malaysia-Thailand Joint Development Area covers an area of about 7,250 sq. km., formed by overlapping continental shelf claims between the two countries. The heart of JDA lies about 180 km from the shores of Pattani province, 260 km from the shores of Songkhla, and 150 km from Kota Bahru in Kelantan State of Malaysia.
The two governments jointly established the Malaysia-Thailand Joint Authority (MTJA) as a juristic entity to assume the rights and responsibilities of both countries in exploration and exploitation of non-living natural resources, particularly petroleum, in JDA. MTJA was empowered to award production sharing contracts to qualified companies.
The two governments agreed on sharing all expenditure and benefits to be derived from petroleum E&P in JDA.
JDA consists of three blocks, namely A-18, B-17, and B-17-01. The companies entitled to enter into contracts with MTJA were those concessionaires or contractors that had won such rights before the 1979 Malaysia-Thailand Memorandum of Understanding came into force. Holding 50% of the rights in each block were the following companies.
CPOC planned 3D seismic exploration covering 300 sq. km. and drilling of a minimum of two wells, and if any of these wells is successful, CPOC is obliged to drill one or two more wells. Development Block A-18 Cakerawala Project CTOC prepared to produce natural gas under the project in the following areas – ranging from production well start-up, depreservation, retesting, to recommissioning and start-up of production facilities – to be ready to deliver first gas at 390 MMcfd on 1 January 2005.
Transmission Pipeline and Malaysia-Thailand Gas Separation Plant Project
The transmission pipeline project was completed in December 2004, as Trans Thai-Malaysia (TTM) commissioned and started up the pipeline around the same period. As for the gas separation plant (GSP-1), about 80% of the work had been completed, and is scheduled for project completion in December 2005.
Phase II Gas Field Development CTOC was prepared to assess the remaining gas contained in Block A-18, as it opened bids for front-end engineering design, EIA, site survey, and soil investigation packages. The company also drilled two appraisal wells: Bumi-2 and Bumi-3.
Block B-17 CPOC studied subsurface data for use in modifying its field development plan and awarded basic engineering design rights to Technip Geoproduction.
Reserves in JDA
As of year-end 2004, the gas reserves* were summarized in the following table (in billion cubic feet, Bcf).
2004 Milestones
Through DMF, the coordination required for the approval of related laws and regulations concerning MTJA was completed during the year, including the following.
|